RemodelinG Guidelines
Complete an Architectural Control Forms and submit 30 days before you start work.
All work must be approved by The Board Of Directors.
Provide the following information
When can work be done at the building Service calls, repairs and construction work are allowed only during the hours of 9:00am to 5:00pm Monday through Friday. Not on weekends or holidays, except in an emergency i.e., Plumbing, Electrical, HVAC, etc.
Please note: YOU MAY NOT move the location of the toilet in the guest or master bathrooms nor any common pipes in the walls.
Hurricane Protection: You must maintain hurricane protection up to the exterior wall of the lanai; both white Roll-Down Shutters and white framed Hurricane glass are acceptable. NOTE: There are drain holes on the floor of all lanai’s. Please make sure these are not blocked when replacing shutters and modifying floor.
All work must be approved by The Board Of Directors.
Provide the following information
- Name of Companies Performing Work and their Certificate of Insurance
- Copy of the Occupational License and a copy of necessary Permits
- Diagrams of modifications drawn to scale.
- Completed Architectural Control Forms
- To protect our elevators during the remodel process.
- To ensure all removal and deliveries utilize the north elevator (which is larger than the south elevator).
- To place the Furniture Pads in the North elevator before any delivery or removal of debris.
- To remove furniture pads at the end of the day.
- For any cost associated with the removal of items from your unit including but not limited old wood, cabinets, boxes, furniture, appliances, mattresses.
When can work be done at the building Service calls, repairs and construction work are allowed only during the hours of 9:00am to 5:00pm Monday through Friday. Not on weekends or holidays, except in an emergency i.e., Plumbing, Electrical, HVAC, etc.
Please note: YOU MAY NOT move the location of the toilet in the guest or master bathrooms nor any common pipes in the walls.
Hurricane Protection: You must maintain hurricane protection up to the exterior wall of the lanai; both white Roll-Down Shutters and white framed Hurricane glass are acceptable. NOTE: There are drain holes on the floor of all lanai’s. Please make sure these are not blocked when replacing shutters and modifying floor.
FLOORING
Both interior and exterior flooring surfaces require specific underlayment products.
Interior Flooring: You must use an underlayment on floors 2-8
Please ensure your installer is using an approved underlayment. The underlayment should go under all interior non-carpeted floor surfaces (tile, wood, laminate, etc.). Casa Bonita I requires: PROFLEX SUPER SIM-90 or Super SAM 125, click button for specifications.
Please ensure your installer is using an approved underlayment. The underlayment should go under all interior non-carpeted floor surfaces (tile, wood, laminate, etc.). Casa Bonita I requires: PROFLEX SUPER SIM-90 or Super SAM 125, click button for specifications.
NOTE: CB1 no longer accepts Pro-Flex® 90
LANAI FLOORS: Lanai floors are constructed to pitch water to the outside (beach side). If you are planning to add, replace, or modify the floor to your lanai, please insure with your contractor that the pitch level is correct to shed water to the outside to prevent water pooling on the floor. There are drain areas on each lanai that cannot be blocked when replacing storm shutters or flooring. No low point or swale where water can pool and permeate through the grout. Exterior Protection: Prior to laying new flooring on the Lanai you must ensure your contractor applies a waterproof membrane directly to the concrete prior to any flooring. Casa Bonita One requires: RedGard® Waterproofing and Crack Prevention Membrane, click button for specifications.
DOORS and LOCKS: Keypad deadbolt AKA touchscreen. Must be Satin Nickel in appearance and it must work with a Schlage Everest C145, 6-pin Key lock cylinder. (keyed to your unit key and our master key).
Electrical: Note: Please provide the following information to your contractor. The electrical service for each unit is 125 AMPS.
WATER HEATER: New water heaters must be installed with a pan under the tank and replaced every 10 years.
DUMPSTER: Contact our Property Manager if you plan to use a "dumpster".
WATER HEATER: New water heaters must be installed with a pan under the tank and replaced every 10 years.
DUMPSTER: Contact our Property Manager if you plan to use a "dumpster".
- You must obtain permission from The Board of Directors to "park" a dumpster on our property.
- Any expense incurred due to City/County code changes will be the responsibility of applicant.
- CB1 trash shoots and dumpsters are not to be used for renovation debris.
NOTE: to help us locate the source of water leaks in the building, please install a utility access door in your bathroom over the toilet (for more information please contact our property manager).